Things are done since 12/20/23

 


Things are done since 12/20/23

[Deck] Cabin top, cockpit, decks fixed, patched, refinished and painted with 2 part Interlux Perfection paint and Kiwigrip non-skid. It took 130 hours of work, 19 work days, during 14 weeks deck painting officially done.

[Deck] New aluminum hatches installed. It required rebuilding deck around hatches.

[Deck] New Fixed windows cut with wire flange and to be able to screw them to cabin top,  reinstalled on DOW795 and screws.

[Cabin] Cabin interior varnishing complete.

[Cabin] Portside lockers painted.

[Cabin] Refinished companion way steps

[Cabin] Put covers on cockpit display back and inverter/charger locker.

[Cabin] Head door installed.

[Cabin] added support planks for refrigerator lid. (small thing).

[Cabin] Slide drawer installed in galley under starboard cockpit sit.

[Electric] Fresh water and Black water tank level indicators installed.  

[Electric] Mast wiring tided up and mast cables gland installed.

[Electric] Replaced all battery cables with right marine grade wires.

[Electric] Installed new battery switches.

[Electric] Battery charge isolator to charge batteries from alternator.

[Electric] Battery monitors installed and monitor display connected.

[Electric] Installed Shore DC power supply.

[Electric] Installed 3KW inverter and lithium 2.5KWh “inverter” battery.

[Electric] Added buzzer on main bilge pump circuit.

[Navigation] Installed RPi based Openplotter and display on nav desk.

[Navigation] Added display signal splitter to duplicate image between Cockpit screen and nav desk.

[Navigation] Mast top wind instruments and Wifi camera installed and connected to Openplotter

[Navigation] Depth finder and log connected to open plotter

[Navigation] Autopilot rudder drive and rudder angle sensor installed and connected.