Day 91. 5/27/23, Fixed window ports reinstallation, AGAIN. Put galley cabinet doors, Air filter frame update, Footpump reinstalled, 10 hours

Galley

Open door installed on the left side and under the stow area.


Electrical.

Front cabin 110V outlet installed.

Air conditioner.

Filter mount updated to accommodate 1" thick12x12" filter. next step - make and install grille.

Interior

Top panel cut in size

Fixed window ports.

Long story short. I found both windows are leaking. Now try to reinstall on VHB tape and 3M 4000UV.

In fact it was a lot of work to clean everything after polyurethane sealer. It bonded to fiberglass 


Foot galley pump

Galley pump rebuilt and installed back. I made detachable pedal plate from SS. 